Calculate Overall Equipment Effectiveness from your shift data, see availability, performance and quality side by side, and find which of the six big losses costs you the most.
Your result
–
Six big losses
Every minute of planned production time ends up either as fully productive time or as one of the six big losses. The biggest bar is usually the best place to start.
Free PDF report
Your results stay free on this page. Share a few details and we will prepare a clean, printable report with your OEE, the A/P/Q breakdown and the six big losses.
The short answer
OEE = Availability × Performance × Quality. Availability is run time divided by planned production time, performance is ideal cycle time × total count divided by run time, and quality is good count divided by total count. The same answer comes from good count × ideal cycle time ÷ planned production time.
Formula
Run time = planned production time − downtime (breakdowns + setups)
Availability = run time ÷ planned production time
Performance = (ideal cycle time × total count) ÷ run time
Quality = good count ÷ total count
OEE = Availability × Performance × Quality = (good count × ideal cycle time) ÷ planned production time
Worked example
A 480-minute shift has two 15-minute breaks and a 30-minute meal break, leaving 420 minutes of planned production time. The machine stops for 47 minutes (27 breakdowns, 20 setups). Its ideal cycle time is 1 second, it makes 19,271 pieces and 18,848 are good.
| Factor | Working | Result |
|---|---|---|
| Run time | 420 − 47 | 373 min |
| Availability | 373 ÷ 420 | 88.81% |
| Performance | (1 s × 19,271) ÷ (373 × 60 s) | 86.11% |
| Quality | 18,848 ÷ 19,271 | 97.80% |
| OEE | 0.8881 × 0.8611 × 0.9780 | 74.79% |
Check: 18,848 good pieces × 1 s ÷ 25,200 s of planned time = 74.79%. These are the example figures loaded in the calculator above.
FAQ
OEE (Overall Equipment Effectiveness) measures how much of your planned production time is truly productive: making only good parts, as fast as possible, with no stops. 100% OEE means perfect production.
85% is widely quoted as world-class OEE for discrete manufacturing, a mark that traces back to Seiichi Nakajima's work on Total Productive Maintenance. The most useful comparison, though, is your own trend over time on the same machine or line.
Put planned time, downtime, ideal cycle time, total count and good count in columns, then add three formula columns: availability = (planned − downtime) / planned, performance = ideal cycle time × total count / run time, quality = good / total. OEE is the product of the three. This calculator applies the same formulas instantly.
No. If it is, the ideal cycle time is set too slow, or the count includes pieces from outside the period. The calculator flags this so you can correct the input.
No. Planned breaks are removed before OEE starts, which is why the calculation uses planned production time. Breakdowns and setups during that time are availability losses.
OEE measures losses against planned production time. TEEP (Total Effective Equipment Performance) measures against all calendar time, so it also shows how much time is not scheduled at all.
Connecting machines through PLCs, sensors or IoT gateways lets you capture run time, stops and counts automatically, with reasons for each stop. That removes manual entry and shows OEE live on a dashboard for every shift.
Keep reading
Tech4LYF has delivered 860+ projects since 2017 across custom software, Odoo ERP and Industrial IoT. Our Chennai team connects machines and builds OEE software and dashboards that capture stops, reasons and counts automatically, every shift.
Or write to [email protected] or call +91 86086 07392
No spam. No pressure. Just a quick discovery call with our experts.